|
Project Overview
Lake Munson is a 225-acre
cypress rimmed lake resulting from the historic impoundment of Munson
Slough. Topographic data and Spanish exploration records suggest that
Munson Slough originally joined the Wakulla River and discharged to the
Gulf of Mexico. Various karst features, such as Ames Sink and the Wakulla
Springs system, apparently developed to capture the slough. Munson Slough
currently terminates at Ames Sink after flowing through approximately
three miles of the Apalachicola National Forest downstream from Lake Munson.
The hydrology of the Munson system was altered by the construction of
"mosquito control ditches" to drain many of the isolated wetlands in the
1940's and 1950's. Natural creeks were extended to provide the outfalls,
making it difficult to be certain what the original drainage area may
have encompassed. The urban development within the City of Tallahassee
also increased the rate and volumes of discharges in the system until
the implementation of stormwater rate control regulations. Ames Sink,
as the receiving water for 72 square miles of drainage area, can be overwhelmed
by the runoff from either a single high-intensity event (March 2-3, 1991)
or a long-duration, high-volume series of events (May through October
1994). There is only 18 feet of fall between the Munson dam and the normal
water elevation at Ames Sink three miles south. Consequently, repeat flooding
of the slough vicinity becomes a more pressing and difficult issue as
the basin continues to develop without volume restrictions.
The review and adoption of the Lake Munson Action Plan occurred during
record flooding throughout Leon County from a series of tropical storms
and depressions. The series of studies on the system were used to prepare
a flood-mitigation project proposal to utilize federal disaster funds.
The $1.96 million in federal Community Development Block Grant flood mitigation
funds provided the up-front monies needed to prepare the surveys, design
drawings and specifications, soil samples, wetland and upland habitat
evaluations, hydrologic and hydraulic models (including groundwater),
and other analyses necessary to obtain the local, state and federal permits
required for the project. The federal funds were also used to acquire
some of the necessary project sites and relocate the affected residents.
The Florida Fish and Wildlife Conservation Commission provided $456,000
to date for the upstream improvements, and $366,000 was awarded through
the USEPA Section 319 Nonpoint Source Management Grant Program. The Leon
County Solid Waste Facility funded $600,000 in hauling costs of sediments
suitable for daily cover. The City of Tallahassee agreed to allow the
County to construct some of the improvements on City property, including
a temporary material handling site. The U.S. Forest Service has permitted
the use of adjacent Apalachicola National Forest property for a material
handling site and access to the sediment delta. The bulk of the funding
for the project is through capital improvement bonds issued by Leon County.
Project costs from concept through construction total $13.3 million, of
which $3.1 million was related to land acquisition and relocation of the
residents. The County Commission recognizes the need to restore and protect
the water bodies within its jurisdiction and is committed to a $26 million
Lakes Restoration Program, with the Lake Munson Restoration Project as
our showcase.
|