The Democrat editorial that appeared earlier this month
titled "School-tax vote's message: Well control our
facilities," provides an excellent opportunity to clear up
some misconceptions the public may have about the
transportation sales tax.In particular, the editorial
leads the reader to believe that local government is
hoarding the revenue generated by the tax. Generally, the
public is not aware that it takes approximately seven years
to plan, design, and purchase right-of-way and begin
construction on a major road-capacity improvement project.
Leon County has accomplished the following sales tax transportation-related
tasks:
Miccosukee Road Phase One
B
planning and design complete with construction scheduled
to begin in January 1996 at a total cost of
approximately $7,500,000.
Miccosukee Road Phase Two
B
planning and 60 percent of the design complete with
construction scheduled for 1998 at a cost of
approximately $10,500,000.
Buck Lake Road B
planning is complete and the design phase is pending
approval of the consultant fee. Buck Lake Road and
Pedrick Road intersection to begin right-of-way
acquisition in mid-1996 and construction in mid-1997.
Total project costs are $3,030,491.
Orange Avenue (from South Monroe to Blair Stone Road)
B
planning and 30 percent design to be complete in roughly
six months. Right-of-way acquisition phase scheduled to
begin in mid-to-late 1996. Total project costs
anticipated to be approximately $900,000.
Old Bainbridge Road Phase One
B
corridor study to begin towards the end of January 1996.
Total project funds programmed from fiscal year
>
96->
97 to 2002-03 equals $8,800,000.
The above projects represent a total of $33,840,491 of the revenue earmarked
for sales-tax transportation improvements in our community. It is good for the
public to view government with a critical eye, but the one-penny local option
sales tax did not make the process of providing transportation facilities
shorter. It made the ability to provide them possible. |